Thruway project moving toward new milestone

May 2, 2017

Of all the transportation improvements planned or already underway since the passage of Act 89 of 2013, few fall into the category of “marquee projects.” One that does is the Central Susquehanna Valley Thruway project, a new, four-lane, 13-mile limited access highway in Monroe Township and Shamokin Dam Borough, Snyder County.

Looking southwest from Ridge Road across PA 147, river, and US 15The project will connect Routes 11/15 north of Selinsgrove to U.S. 15 south of Winfield and include a connector from the new highway to the Veterans Memorial Bridge on Route 61. Projected for completion in 2024, it will separate trucks and through traffic from local traffic, reducing congestion, improving safety and spurring economic growth.

Work on the northern section has commenced. The project will reach another milestone May 25 when PennDOT unveils a first draft of the southern section during a public meeting at Selinsgrove Middle School. The meeting is at 6:30 p.m.

In February, PennDOT announced that several environmental and engineering challenges had surfaced, requiring some route modifications. The proposed alternatives will be unveiled at the meeting, and PennDOT hopes to identify the preferred alternative later this year.

“Nearly every project funded by Act 89 will improve safety, reduce congestion and accommodate economic growth in some manner, but the thruway project is really a shining example,” said PHIA Managing Director Jason Wagner. “We hope to have more of these kinds of projects that will add capacity once we bring the existing highway infrastructure up to a better state of repair in the years ahead.”

 